OK WELL THINGS HAVE BEEN BUSY
ALREADY AUGUST 13TH!! WOW
HERE'S OUR UPDATE
After the pool floor area was stabilized with larger rock they filled the area with a layer of concrete and then lined the cavity with heavy plastic sheeting
Next came the rigid foam insulation
then the steel for the pool floor and walls and the cement truck arrives to pour the pool floor
the pour begins after much environmental damage positioning the cement pump and the truck
everyone is engaged in the pour
Almost done
Leveled as they went
Then the finishing machine smooths everything out
Next morning forming up for pouring the walls
Lots of steel (i thought we were putting in a prison)
Pool takes shape after pour and forms removed
rough plumbing goes in
Crew moves excess dirt from outside wall into the inner cavity and also cleans up the area
area looks much better after cleanup
Inner cavity/floor area is back filled to get ready for pouring floor
Floor drains go in
Ready for pouring of floor
Walls have gone up quickly
Ane on inspection tour
Almost ready for roof beams