Well progress has been made this week
here is our posting for August 22nd
They first installed more horizontal steel for the wall top cap
when that was poured all the way around they laid more brick on the back wall and installed yet another row of steel and cement for the final cap
Here is a shot of the back wall with window openings and final height
Mean while they started coating the raw bricks with cement - here is how they do it
Front wall is finished this weekend
It will be painted white later to match the house
at the far end the roof of the mechanical room takes shape
After much deliberation we chose our tiles for the pool and floor and they have arrived
They started the finish on the interior walls and should be finished with all wall finishing by end of next week.
Back and frount walls stand ready for the roof beams
and we took delivery of the beams after Hugo our job manager hand picked them out in Otavallo
We are accumulating quite a large amount of scrap wood from forms for concrete work. We will have lots of firewood to cut up when done.
See ya next week