Sunday, September 11, 2011

Week 10

This week there is not much visual change, the walls are almost all up for the first floor and they started and almost finished the rebar and cement top ring. Here is the X spot photo for week 10.

Here is a detail of the finished and still formed sections of the ring, last weeks entry has photos of the rebar that is inside of the cement ring. This ties the walls together at the top and the vertical rebar sticking up will attach the roof beams to the walls.

The Yoga room with its large arched window took shape this week.

Here is a view down the hallway towards the entrance tower from the bedroom area.

The view from the backyard shows the Dining area taking shape on the left and the unfinished fireplace chimney in the center.

All in all from the front as you approach the house is starting to take shape. Here are the entry way and to the right, the garage.