Week 29, January 21, 2012


OK here we go again.
This week the rainy season hit with a vengeance, we had heavy rains the last three nights. Not much rain during the day just a few scattered showers in the late afternoon. 
Here is as close as I could get to the X spot this week due to the mud.


Ane enters thru the Garage over newly installed cement floors. We got 90 % of the cement slab floors poured in two days this week.


Here from the far corner of dining room we see coated interior walls, concrete slab (we now have to wait 28 days for them to cure before the hardwood floor installer will start) also note the electrical and plumbing stubs for the kitchen island.


view from opposite corner in great room.


Here in the last area poured friday afternoon we have evidence of a fairly large dog visiting that evening.


Inside all the walls have been skim coated with cement and adobe mixture, while outside just a small area on the second floor and the outside of the circular entryway are left to do. The front entrance will have a small porch to shelter visitors waiting at the door probably will be added when the rest of the roof is finished with tile installation.


and from the front.


Meanwhile across the way our neighbors Julio and Paula's house is taking shape.


More to come.